Timeline & Progress Updates

Project Timeline

 

PROGRESS UPDATES

March 10, 2020

Major progress has been made on site since the last update. Excavation was completed at the beginning of February and construction quickly moved into placing and pouring footings that will become the base structural support of the building.

Read more about March 10, 2020
December 10, 2019

Phase 1 is nearly complete: the maintenance shed, storm drain, asphalt are finished. Planting around the perimeter continues and special care is being taken to save the sequoyah on the southwest corner of the project site.

Read more about December 10, 2019

 